Out For Tender › Vereinigte Staaten › Bauarbeiten
Z1DA--554-26-106 Replace DW Valves.
- Auftraggeber
- NETWORK CONTRACT OFFICE 19 (36C259), Veterans Affairs, Department of
- Land
- Vereinigte Staaten
- Kategorie
- Bauarbeiten
- Frist
- Endet in 6 Tagen (30 Sep 2026 10:00 UTC-6)
- Veröffentlicht
- 15 Sep 2026
- Verfahren
- Solicitation - Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14)
Offizielle Bekanntmachung lesen und bieten → Die Angebotsabgabe erfolgt immer auf dem Portal des Auftraggebers, niemals hier.
Was der Auftraggeber sucht
N AMENDMENT TO SOLICITATION 36C25926R0057 POSTED ON SEPTEMBER 15, 2026. The purpose of this amendment is to : To extend due date for proposals from September 16, 2026, to September 30, 2026, at 10 AM. MT. RFIs will be responded in a second amendment at later date before proposals due date. To post site visit documents : All offers please email them to Elia L Ruiz Manzo at Elia-Laritza.Ruiz-Manzo@va.gov. All other items and conditions remain the same. List of Attachments See attached document: Site Visit Meeting Doc. See attached document: Site Visit Attendance_FE. ---------------------------------------------------------------------------------------------------------------------------------------------------------- OBJECTIVE The Department of Veterans Affairs has a requirement to install valves on water supply lines to enable individual building isolation from the campus water supply at the Rocky Mountain Regional VA Medical Center. Facility Management Services has identified approximately 30 valves on domestic cold water, domestic hot water, and domestic hot water return that require valve installation or valve replacement. The intent of this contract is to install isolation shutoff valves on the domestic cold water (DCW), domestic hot water (DHW), and domestic hot water recirculation (DHWR) pipes at key points to allow facilities maintenance to control water flow to individual buildings. STATEMENT OF WORK In phase 1, the contractor shall: For Building A: Coordinate an 8 hour water shutoff with the COR. This shutdown will likely be scheduled weekday-overnight or weekend-daytime. The DCW/DHW/DHWR shutoffs shall be accomplished using dual ice plugs on each pipeline. The contractor shall position the ice plugs such that a mid-section of pipe can be removed and replaced with a pre-built pipe section that includes a shutoff valve. Ensure the pre-built section and installation effort are conducted at an appropriate cleanliness level for domestic water supply. Install the pre-built pipe section and utilize pipe connections that are grooved coupling or flange as appropriate for the use-case and installation scenario. Re-insulate installed pipe sections. Pipe, valve, and connection/coupler material and sizes shall be appropriate for the use-case and installation scenario. For Building E: Coordinate an 8 hour water shutoff with the COR. This shutdown will likely be scheduled weekday-overnight or weekend-daytime. The DCW/DHW/DHWR shutoffs shall be accomplished using dual ice plugs on each pipeline. The contractor shall position the ice plugs such that a mid-section of pipe can be removed and replaced with a pre-built pipe section that includes a shutoff valve. Ensure the pre-built section and installation effort are conducted at an appropriate cleanliness level for domestic water supply. Install the pre-built pipe section and utilize pipe connections that are grooved coupling or flange as appropriate for the use-case and installation scenario. Re-insulate installed pipe sections. Pipe, valve, and connection/coupler material and sizes shall be appropriate for the use-case and installation scenario. For Building G: Coordinate an 8 hour water shutoff with the COR. This shutdown will likely be scheduled on a Sunday. The DCW/DHW/DHWR shutoffs shall be accomplished using dual ice plugs on each pipeline. The contractor shall position the ice plugs such that a mid-section of pipe can be removed and replaced with a pre-built pipe section that includes a shutoff valve. Ensure the pre-built section and installation effort are conducted at an appropriate cleanliness level for domestic water supply. Install the pre-built pipe section and utilize pipe connections that are grooved coupling or flange as appropriate for the use-case and installation scenario. Re-insulate installed pipe sections. Pipe, valve, and connection/coupler material and sizes shall be appropriate for the use-case and installation scenario. For Building D+F: Coordinate an 8…
Sprache dieser Bekanntmachung: English. Titel und Beschreibung erscheinen genau so, wie der Auftraggeber sie veröffentlicht hat.
Source: SAM · reference 36C25926R0057 · JSON